Runway 10/28 ILS project information including runway closures (UPDATED)

The contractor has reworked the schedule to reduce the runway closures. While the project will begin on April 29th, runway closures are estimated to begin 3 weeks later. Runway 10/28 will remain on a nightly closure schedule and runway 4/22 will be closed for the entire week runway closures are estimated to last. If you have questions please call Airport OPS.

Executive Hangar Reconstruction Area B Phase 4

Next Phase of Construction

Phase 3 will be completed very soon and the contractor will move to Phase 4 on April 25th. This phase is projected to take 60 days without any difficulties or delays. Please contact Avion regarding any aircraft movement and/or storage.

 

Phase 4

Airport Board 3/19/13

Enplanements

January 2013 vs. January 2012
American rose 16.1%
Southwest down 5.2%
United rose 16.2%
Overall up 2.2%

February 2013 vs. February 2012
American rose 16.4%
Southwest down 12.2%
United up 8.3%
Overall down 3.5% (due to the leap year, we saw the same drop in numbers in 2008)

Overall we are up 1.1% on the year over last year.

We are above the 7 year average in every month of the fiscal year so far.

Construction

Executive Hangar Reconstruction Area A
Is just about to be finished. There is a few patching items left to be completed. A punch list will be created and addressed to finish the project.

Executive Hangar Reconstruction Area B
Jones Brothers should be completed with Phase 2 and will move on to Phase 3 the 25th.

Northwest Taxiway Extension Project
Roadways have been completed and the hangars are in the final phases of completion.

New Parking Construction
Bids should be announced in May and the plan is to have the lot open by the Thanksgiving Holiday.

XCOR

Spaceport Application
Progress is continuing, we along with the FAA are trying to iron out the details to get the airport approved for spaceflight. Keep in mind we are attempting to become the first Part 139 certificated airport with active air carrier flights to be certified as a spaceport.

Next Meeting

Regional Airport Board
TBD

Airport Planning Board
May 21, 2013 @ 9:00AM

Executive Hangar Reconstruction Area B Phase 3

Next Phase of Reconstruction

Phase 2 will be completed by the 25th of March and the contractor will immediately move to Phase 3 on the 25th.  This phase is projected to take 60 days without difficulties or weather delays.  Please contact Avion regarding any aircraft movement and/or storage.  The XCOR Hangar is not available for use.

Hangars Phase 3

Executive Hangar Reconstruction Area B Phase II

The phase is scheduled to begin the 24th of January. This phase is projected to take 60 days without difficulties or weather delays.  Please contact Avion regarding any aircraft movement or storage.

Phase 2

Airport Board Meeting 1/15/13

Enplanements

For December 2012 we were down 1.4% over December 2011 (40,984 vs. 41,548).  We had 2,000 more seats in the market for December 2012 over December 2011. We are still trending above the 7 year average for every month in the fiscal year so far.

Executive Apron Reconstruction Area A

The contractor has begun work on the final phase last week, this is the area immediately to the north of Avion. The last phase should take 60 days to complete. The remaining concrete work including the drainage gutters should be complete by the end of the week depending on weather and availability.

Executive Apron Reconstruction Area B

The contractor has completed work on Phase 1 and the area has been reopened. A meeting has been scheduled to discuss the next phase of the project before it begins. All displaced aircraft have been returned to their respective hangars.

Northwest Taxiway Extension Project

Phase II (the entrance roadway and utilities) of this project are underway according to the contractor.  The contractor has begun curb and gutter work in the area and the roadways should be constructed in the next 30 days.

Next Airport Board Meeting

The next airport board meeting will be February 19th at 9:00 AM

Executive Hangar ramp reconstruction Hangars A-D

Executive Hangar Phase 2 area 1 is complete. Hangars A-D are accessible by aircraft. We haven’t received a start date on the next section.

Executive Hangar Ramp construction progess

Both projects are progressing, but due to the rain we are not being given completion dates. As soon as the contractors and engineers have any information on completion we will pass it on. Thank you for your patience.

Executive Hangar construction update for pavement near Hangars A-D

Jones Brothers has advised us they plan on paving on Saturday (1/5) and Sunday (1/6) in that area.

Executive Hangar Apron Project near Hangars A-D, UPDATE 12/27/12

We have just received an update on the construction project in that area with a new estimated completion date of Friday, January 4, 2013.  Jones Brothers had an equipment issue at the plant that produces their asphalt.  They are attempting to remedy the issue as soon as possible.  We will keep you advised of any changes or updates when we receive them.