August Airport Board Meeting

Enplanements

July saw all three airlines have positive growth months over last year.  The three combined average a 9.5% increase over July of 2011.  YTD we are up 4.8%

We are trending above the 9 year average in every month of the fiscal year so far.

Over the last two months we have had more enplanements than Lubbock.

Construction

Airfield

The painting contractor anticipates having all the painting completed by the second week of September.

Executive Hangars

The executive hangar construction is progressing currently with the concrete drainage gutters in Phase 3.  That phase should be completed in the next 2-3 weeks and Phase 4 should be started prior to the next airport board meeting.

The next apron reconstruction project has been accelerated.  Due to XCORs lease of the AMI hangar displaced pilots and aircraft will not have a location to store their aircraft.  We have asked Jones Brothers to begin work as soon as possible so we can have the greatest number of tenants displaced and moved back in prior to the AMI hangar being turned over to XCOR.

 

Northwest Taxiway Extension Project

Roadway work and utility work has begun and should be completed in the next 6-8 weeks. Construction has begun on the first two hangars.

Airport Parking

A parking discussion has been scheduled during the September 11th City Council briefings.

 

CAF

The CAF is hosting a Mustang Stampede this Saturday the 25th.  For more information please visit http://www.commemorativeairforce.org/?page=cms/event&eventID=153

 

Next Airport Board Meeting

The next airport board meeting is Tuesday, September 18, 2012.

RWY 10/28 and RWY 16L/34R UPDATE

RWY 16L/34R was closed this morning for the transition to the RWY 28 end of the PAPI project being done by the Federal Aviation Administration (FAA). We have been told by the FAA the runway and approaches are to be flight checked on September 10th. If the approaches and PAPIs are certified we anticipate opening the runways shortly after that when the project has been signed off by the FAA.

Airport Board Meeting 6/19/12

Progress Report

Up 2.8% over May of 2011.  For the year we are up 3.5%.

Fuel Sales are down in all sectors other than Airline/Cargo customers.

We are month over month over the nine year average.

Updates

Rehabilitate Taxiway Systems

Painting still needs to be completed on TWYs A, B, M, P, W. A hold short marking is missing on TWY W prohibiting us from opening RWY 16L/34R.  Winds have prevented the painting contractor from actually laying out the markings.

Executive Apron Reconstruction

Phase 2 will have hot mix applied in about 2 weeks and should be completed by the next meeting.

The next major project in the executive hangar area that will be done is the reconstruction of all the ramp areas near the hangars west of the current work. It will be broken down into phases so only a few hangars are displaced at a time.

Old East Hangar

The building has been taken down and the final debris removal is being finished.

2012 Disaster Exercise (DisEx)

The disaster exercise went very well.  We had all the local law enforcement and mutual aid responders show up.  the local area hospitals also participated to earn mass casualty credit.

Visit our Flickr page to see photos of the day.

http://www.flickr.com/photos/midlandairport/sets/72157630211090242/

 

Aviation Summit

See Aviation Summit Post

Parking Lot Addition

A feasibility study has been done on a vacant lot west of the existing parking lots with three phases.  Whether or not it is covered is an additional cost consideration that needs to be discussed. Initial estimates show the cost to construct the lot will double if the lot is covered. A construction proposal will be drafted to submit to the board at the next meeting.

The Green section is the "proposed" Phase 1

Southwest Airlines Flight Schedule

Starting in November 2012 Southwest will add an extra Houston and Las Vegas flight.  As a result of those additions we will lose a Dallas flight.  A net gain and a positive sign that Southwest believes in Midland’s passenger base.  We hope to see a new 737-800 on some of those flights.

The next meeting is Tuesday, August 21, 2012 @ 9:00 a.m.

RSAT Meeting June 27th at 10AM

Located in the Media Room on the third floor of the Terminal Building.

Agenda:

10:00- Introductions

10:15- Incident/Incursion Reviews for the past 12 months

10:45- Airport Management updates/concerncs

11:15- FAA air Traffic updates/concerns

11:45- Break

12:00- Airline updates/concerns

12:20- FBO updates/concerns

12:40- General Aviation concerns

13:00- Development of action plan

14:20- Final thoughts and adjournment