Runway 10/28 ILS project information including runway closures (UPDATED)

The contractor has reworked the schedule to reduce the runway closures. While the project will begin on April 29th, runway closures are estimated to begin 3 weeks later. Runway 10/28 will remain on a nightly closure schedule and runway 4/22 will be closed for the entire week runway closures are estimated to last. If you have questions please call Airport OPS.

Executive Hangar Reconstruction Area B Phase 4

Next Phase of Construction

Phase 3 will be completed very soon and the contractor will move to Phase 4 on April 25th. This phase is projected to take 60 days without any difficulties or delays. Please contact Avion regarding any aircraft movement and/or storage.

 

Phase 4