Airport Board Meeting 1/15/13

Enplanements

For December 2012 we were down 1.4% over December 2011 (40,984 vs. 41,548).  We had 2,000 more seats in the market for December 2012 over December 2011. We are still trending above the 7 year average for every month in the fiscal year so far.

Executive Apron Reconstruction Area A

The contractor has begun work on the final phase last week, this is the area immediately to the north of Avion. The last phase should take 60 days to complete. The remaining concrete work including the drainage gutters should be complete by the end of the week depending on weather and availability.

Executive Apron Reconstruction Area B

The contractor has completed work on Phase 1 and the area has been reopened. A meeting has been scheduled to discuss the next phase of the project before it begins. All displaced aircraft have been returned to their respective hangars.

Northwest Taxiway Extension Project

Phase II (the entrance roadway and utilities) of this project are underway according to the contractor.  The contractor has begun curb and gutter work in the area and the roadways should be constructed in the next 30 days.

Next Airport Board Meeting

The next airport board meeting will be February 19th at 9:00 AM